Millstream Bridge, Mill Street, Central Reading for Reading Borough Council.

The project which was completed in 11 weeks resulted from a requirement to increase the load capacity of Millstream Bridge, a structure comprising 3 brick arches and concrete box culvert running across the full width of the deck.

The project involved complete clearance of the culvert, confined space requiring hand digging, and installation of corrugated galvanised steel liners under the existing brick arches, the void being grouted and the whole being waterproofed.

Download this case study here


Guildford Town Wharf for Guildford Borough Council.

A project to improve the Town Wharf in Central Guildford located in a conservation area alongside the River Wey.

The project involved installing internally lit aluminium fins mounted on seasoned oak uprights and fixed to an existing wall, re paving the wharf pavement with granite setts and installing seasoned oak raised planters throughout.

Download this case study here